· Temp Fence – 7th April
· Site Cut & Toilet – 7th April
· Set Out & Bin – 8th April
· Electricity – 10th April
· Drains – 13th April
· Bored Piers – 9th April
· Slab Start – 15th April
· Slab Pour – 17th April![]() |
Temporary fencing was finally put up |
Site cut, Set Out, Bin and toilet installed on 8th and 9th of April 2015.