They aren't all roses... (Pre-plaster stage)

In a number of locations the mixers or the water outlet has been installed via notching the studs depth by 30 mm or greater

There are a number of bowed/out of alignment walls in the home that exceeded the allowance of 4 mm tolerance over 2 m. These walls have been marked with pink spray paint (B or OOA).

The rough in of the plumbing and electrical breaches AS 1684.2-2006

The cooling pipes and gas pipes running over the trusses have not been fixed at 1.50m intervals as required in the plumbing code

Incomplete roof tiling and front facade flashings missing to the dwelling

Temporary downpipes have not been installed to direct water away from the slab

RHS - the stop end barge soakers has not been waterproofed with lead at its junction to the roof tiles

A section of sarking not fully installed