Marlow 25

Marlow 25

Thursday, 28 May 2015

The fix

These pictures below shows the fixes that have been done by the builder based on the inspection reports that Darbecca provided. We've found independent inspection really worth it as Carlisle Homes does not provide inspection on pre-plaster stage - they only use the site supervisor to inspect the pre-plaster stage. 


A piece of timber has been bolted to support the overhanging frame

Intersecting wall block connections have now had two nails instead of just one
Intersecting wall block connections have now had two nails instead of just one

The bulkhead has now been constructed with a lintel
Linings have been installed to the frame

A supporting timber to the stud has been installed to the area where the notch has taken place

A section of floor has been leveled 

A section of floor has been leveled  

A section of floor has been leveled 

A section of floor has been leveled 

Noggins has been installed at the bottom of the box
Temporary downpipe is finally installed

Our SS told me that Carlisle Homes only provide four temporary downpipes. If we do not use independent inspector, we will never pick up this issue. Unbelievable looking at the way they are trying to save cost.

No comments:

Post a Comment